KENNEDY SPACE CENTER SHUTTLE & PAYLOAD PROCESSING STATUS REPORT Tuesday, Sept. 18, 2001 (12 p.m.) NOTE: This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights. Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC Home Page for the latest schedule of future Shuttle missions. MISSION: STS-108 - 12th ISS Flight (UF1) - MPLM VEHICLE: Endeavour/OV-105 TARGET KSC LAUNCH DATE/TIME: Nov. 29, 2001 at 8:05 p.m. EST TARGET KSC LANDING DATE/TIME: Dec. 10, 2001 at 12:26 p.m. MISSION DURATION: 10 days CREW: Gorie, Kelly, Godwin, Tani; (ISS up) Onufrienko, Bursch, Walz; (ISS down) Culbertson, Dezhurov, Turin ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: Technicians have completed installation of Endeavour's drag chute. Work on the orbiter's auxiliary power unit (APU) tank struts continues, while technicians continue APU quick disconnect replacement efforts. Technicians are also installing an enhanced monoball wiring harness that will improve processing efficiency down stream. MISSION: STS-109 - HST Servicing Mission 3B VEHICLE: Columbia/OV-102 TARGET KSC LAUNCH DATE/TIME: Jan. 17, 2002 at 3:52 a.m. EST (under review) TARGET KSC LANDING DATE/TIME: Jan. 28, 2002 MISSION DURATION: 11 days CREW: Altman, Carey, Grunsfeld, Currie, Newman, Linnehan, Massimino ORBITAL INSERTION ALTITUDE and INCLINATION: 308 nautical miles/28.5 degrees Shuttle Processing Note: Columbia was powered up over the weekend. Routine checks on the recently installed right hand orbiter maneuvering system (OMS) pod continue. Installation of the left hand OMS pod is scheduled begin today and the forward reaction control system will be installed later this week. MISSION: STS-110 - 13th ISS Flight (8A) - ITS S0, MT VEHICLE: Atlantis/OV-104 TARGET KSC LAUNCH DATE/TIME: Feb. 28, 2002 (under review) TARGET KSC LANDING DATE/TIME: March 9, 2002 MISSION DURATION: 9 days CREW: Bloomfield, Frick, Ross, Smith, Ochoa, Morin, Walheim ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: Orbiter Atlantis and orbiter Discovery swapped locations yesterday. Workers will now resume Atlantis' processing for the STS-110 mission. STRUCTURAL INSPECTION & MODIFICATION PERIOD VEHICLE: Discovery/OV-103 Shuttle Processing Note: Orbiter Discovery yesterday began a temporary storage period expected to last until late October. Orbiter Discovery is scheduled to begin a thorough structural inspection and modification period. Shuttle managers continue to assess the content, schedule and location of this planned work period. -- end --