KENNEDY SPACE CENTER SHUTTLE & PAYLOAD PROCESSING STATUS REPORT Thursday, Sept. 27, 2001 (12 p.m.) NOTE: This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights. Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC Home Page for the latest schedule of future Shuttle missions. MISSION: STS-108 - 12th ISS Flight (UF1) - MPLM VEHICLE: Endeavour/OV-105 TARGET KSC LAUNCH DATE/TIME: Nov. 29, 2001 at 8:05 p.m. EST TARGET KSC LANDING DATE/TIME: Dec. 10, 2001 at 3:26 p.m. MISSION DURATION: 11 days CREW: Gorie, Kelly, Godwin, Tani; (ISS up) Onufrienko, Bursch, Walz; (ISS down) Culbertson, Dezhurov, Turin ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: Orbiter Endeavour's main engines have been installed and final connections are in work today. Engine leak checks will follow tomorrow. Workers have completed routine tests of the crew module lighting system and Ku band testing is ongoing. Preparation is under way for tomorrow's Crew Equipment Interface Test. Over the weekend, technicians will retorque an auxiliary power unit (APU) quick disconnect and begin ammonia system servicing. The orbiter's wiring harness modification continues. MISSION: STS-109 - HST Servicing Mission 3B VEHICLE: Columbia/OV-102 TARGET KSC LAUNCH DATE/TIME: Jan. 17, 2002 at 3:52 a.m. EST (under review) TARGET KSC LANDING DATE/TIME: Jan. 28, 2002 MISSION DURATION: 11 days CREW: Altman, Carey, Grunsfeld, Currie, Newman, Linnehan, Massimino ORBITAL INSERTION ALTITUDE and INCLINATION: 308 nautical miles/28.5 degrees Shuttle Processing Note: Installation of Columbia's forward reaction control system is complete. Work continues on both orbiter maneuvering system (OMS) pods and the OMS pod cross-feed lines will be connected tomorrow. Functional testing of the flash evaporator system continues. Forward reaction control system installation begins this week. MISSION: STS-110 - 13th ISS Flight (8A) - ITS S0, MT VEHICLE: Atlantis/OV-104 TARGET KSC LAUNCH DATE/TIME: Feb. 28, 2002 (under review) TARGET KSC LANDING DATE/TIME: March 9, 2002 MISSION DURATION: 9 days CREW: Bloomfield, Frick, Ross, Smith, Ochoa, Morin, Walheim ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: Technicians have completed draining Atlantis' OMS manifold and thruster replacement work begins this weekend. The monoball wiring harness modification continues. The orbiter's fuel cell testing begins Saturday. STRUCTURAL INSPECTION & MODIFICATION PERIOD VEHICLE: Discovery/OV-103 Shuttle Processing Note: Orbiter Discovery remains in temporary storage through late October. Discovery is scheduled to begin a thorough structural inspection and modification period. Shuttle managers continue to assess the content, schedule and location of this planned work period. -- end --