KENNEDY SPACE CENTER SHUTTLE & PAYLOAD PROCESSING STATUS REPORT Monday, Nov. 19, 2001 (11:30 a.m.) NOTE: This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights. Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC Home Page for the latest schedule of future Shuttle missions. MISSION: STS-108 - 12th ISS Flight (UF1) - MPLM VEHICLE: Endeavour/OV-105 TARGET KSC LAUNCH DATE/TIME: Nov. 29, 2001 at 7:41 p.m. TARGET KSC LANDING DATE/TIME: Dec. 10, 2001 at 3:16 p.m. MISSION DURATION: 10 days, 20 hours CREW: Gorie, Kelly, Godwin, Tani; (ISS up) Onufrienko, Bursch, Walz; (ISS down) Culbertson, Dezhurov, Tyurin ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: At Pad B, launch processing operations for Shuttle Endeavour continue on schedule. Over the weekend, early stowage was completed, the replacement yaw actuator for main engine No.2 was tested successfully and the three EVA suits were installed and checked out in the airlock. Ordnance installation and connections are in progress and aft closeouts continue. No work is scheduled for the Thanksgiving holidays (Thursday and Friday). This weekend, preparations will get underway to start the final countdown, scheduled for 11 p.m. Monday, Nov. 26. The seven STS-108 crewmembers will arrive at KSC at 4 p.m. Sunday, Nov. 25. MISSION: STS-109 - HST Servicing Mission 3B VEHICLE: Columbia/OV-102 TARGET KSC LAUNCH DATE: Feb. 14, 2002 TARGET KSC LANDING DATE: Feb. 25, 2002 MISSION DURATION: 11 days CREW: Altman, Carey, Grunsfeld, Currie, Newman, Linnehan, Massimino ORBITAL INSERTION ALTITUDE and INCLINATION: 308 nautical miles/28.5 degrees Shuttle Processing Note: Pre-launch processing of Columbia continues in the Orbiter Processing Facility (OPF). Airlock verification is in work and preparations are underway to perform Auxiliary Power Unit (APU) leak and functional tests and install the main engine heat shields later this week. MISSION: STS-110 - 13th ISS Flight (8A) - ITS S0, MT VEHICLE: Atlantis/OV-104 TARGET KSC LAUNCH DATE: March 21, 2002 TARGET KSC LANDING DATE: April 1, 2002 MISSION DURATION: 11 days CREW: Bloomfield, Frick, Ross, Smith, Ochoa, Morin, Walheim ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: Atlantis is powered down in its OPF bay as scheduled modification work continues through mid December. STRUCTURAL INSPECTION & MODIFICATION PERIOD VEHICLE: Discovery/OV-103 Shuttle Processing Note: Deservicing work on Orbiter Discovery is in process in the OPF as Shuttle managers continue to assess the content, schedule and location for the structural inspection and modification down period. The left orbital maneuvering system (OMS) pod has been removed and work is in progress to remove the right pod. Discovery will be rolled back for temporary storage in the Vehicle Assembly Building next week. -- end --