KENNEDY SPACE CENTER SHUTTLE and PAYLOAD PROCESSING STATUS REPORT Thursday, June 21, 2001 (12:30 p.m.) NOTE: This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights. Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC Home Page for the latest schedule of future Shuttle missions. MISSION: STS-104 - 10th ISS Flight (7A) - Airlock VEHICLE: Atlantis/OV-104 LOCATION: Pad 39B TARGET KSC LAUNCH DATE/TIME: NET July 12, 2001 at 5:04 a.m. EDT TARGET KSC LANDING DATE/TIME: July 23, 2001 at 1:03 a.m. MISSION DURATION: 10 days and 19 hours and 59 minutes CREW: Lindsey, Hobaugh, Kavandi, Gernhardt, Reilly ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: Space Shuttle Atlantis arrived at Launch Pad 39B at 10:50 a.m. today. Processing continues on schedule for a launch date no earlier than July 12. Launch pad validations are in work through Friday. The STS-104 flight crew will participate in Terminal Countdown Demonstration Test activities late next week. The launch day dress rehearsal culminates with a simulated main engine cutoff on Friday, June 29. Shuttle and Space Station managers will assemble at KSC June 28 for the STS-104 Flight Readiness Review. Payload Processing Note: The U.S. Airlock will be installed into Atlantis' payload bay on June 26. The flight crew will conduct final payload inspections on June 28 prior to closing the payload bay doors later that day for flight. The IMAX 3D camera has been delivered to the pad and will be installed into the orbiter June 23. MISSION: STS-105 - 11th ISS Flight (7A.1) - Leonardo MPLM VEHICLE: Discovery/OV-103 LOCATION: VAB high bay 3 TARGET KSC LAUNCH DATE/TIME: NET Aug. 5, 2001 at 7:05 p.m. TARGET KSC LANDING DATE/TIME: Aug. 17, 2001 at about 3:30 p.m. MISSION DURATION: 11 days, 20 hours and 25 minutes CREW: Horowitz, Sturckow, Barry, Forrester; (ISS up) Culbertson, Dezhurov, Turin; (ISS down) Usachev, Voss, Helms, ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: Space Shuttle Discovery remains in VAB high bay 3 undergoing final preparations for rollout to Launch Pad 39A no earlier than June 27. Technicians will replace one of the orbiter's multiplexer-demultiplexers Friday night. Payload Processing Note: In the Space Station Processing Facility, leak checks and heater testing has been conducted on the Leonardo MPLM as multi-layer insulation installation continues in work. Leak checks of the Common Berthing Mechanism continue this week. The MPLM will be delivered to the pad in late July for launch no earlier than Aug. 5. MISSION: STS-108 - 12th ISS Flight (UF1) - Raffaello MPLM VEHICLE: Endeavour/OV-105 LOCATION: Orbiter Processing Facility bay 1 TARGET KSC LAUNCH DATE/TIME: Nov. 29, 2001, at 8:05 p.m. TARGET KSC LANDING DATE/TIME: Dec. 9, 2001 MISSION DURATION: 10 days CREW: Gorie, Kelly, Godwin, Tani; (ISS up) Onufrienko, Bursch, Walz; (ISS down) Culbertson, Dezhurov, Turin ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees Shuttle Processing Note: Routine orbiter system testing is in work and a powered down modification period is now under way. Payload Processing Note: Post-flight processing of the Raffaello Multi-Purpose Logistics Module in the Space Station Processing Facility continues. Environmental Control and Life Support (ECLSS) checks also continue. MISSION: STS-109 - HST Servicing Mission 3B VEHICLE: Columbia/OV-102 LOCATION: OPF bay 3 TARGET KSC LAUNCH DATE/TIME: Jan. 17, 2002 TARGET KSC LANDING DATE/TIME: Jan. 28, 2002 MISSION DURATION: TBD CREW: Altman, Carey, Grunsfeld, Currie, Newman, Linnehan, Massimino ORBITAL INSERTION ALTITUDE and INCLINATION: 308 nautical miles/28.5 degrees Shuttle Processing Note: Technicians are inspecting the orbiter's chin panel and nose cap. Standard subsystem testing is ongoing. -- end --