KENNEDY SPACE CENTER SHUTTLE and PAYLOAD PROCESSING STATUS REPORT Tuesday, Aug. 7, 2001 (5 p.m.) Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC Home Page for the latest schedule of future Shuttle missions. MISSION: STS-105 - 11th ISS Flight (7A.1) - Leonardo MPLM VEHICLE: Discovery/OV-103 LOCATION: Launch Pad 39A TARGET KSC LAUNCH DATE/TIME: Aug. 9, 2001 at 5:38 p.m. EDT TARGET KSC LANDING DATE/TIME: Aug. 21, 2001 at about 1:17 p.m. MISSION DURATION: 11 days, 19 hours and 39 minutes CREW: Horowitz, Sturckow, Barry, Forrester; (ISS up) Culbertson, Dezhurov, Turin; (ISS down) Usachev, Voss, Helms, ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees Launch - 2 days: Launch countdown activities continue on schedule today. Operations to load the Power Reactant and Storage Distribution system tanks with cryogenic reactants are set to begin late this afternoon. Loading operations are scheduled to be completed by early tomorrow morning, at which time the orbiter mid-body umbilical unit will be demated. Later tomorrow, the communications system on the Shuttle will be activated and tested and the rotating service structure will be moved to the launch position at about 9:30 p.m. On Thursday beginning at about 8:45 a.m., the external tank will be loaded with its complement of 500,000 gallons of liquid cryogenic propellants. The crew will depart for the pad at 1:47 p.m. Weather forecasters are currently indicating a 40 percent chance that weather could prevent launch on Thursday. The primary concerns are for showers and thunderstorms in the vicinity of the launch pad. At launch time on Thursday, clouds will be scattered at 4000 feet, 10,000 feet and 25,000 feet. Winds will be from the southeast at 10 - 14 knots. Temperature will be 82 degrees, F. and humidity 74 percent. Forecasters call for a 70 percent chance of violation for a 24-hour and 48-hour delay. -- end --